This mode applies to specific APS optimizations. It allows you to bring greater precision to your configuration when preceding/subsequent task links are present.

Preliminary processing of the links is required before launching a specific APS optimization (or APS+).

This processing is done by :

- Selecting the desired date range for your horizon

- Checking "Process link levels"

- Selecting "Infinite" in the "Resource capacity" option under Calendars.

Once the first step has been completed, unchecked this box and go back to "Finite" Resource capacity. After any modification or addition of links, or addition, we recommend you repeat this procedure.